Site preparation and maintenance for a Clark polyethylene
tank
Download Recommended Site Installation Sheet
- Ensure the location of the tank is level,
stable ground which has uniform compaction (free of soft spots).
Do not locate large water tanks close to retaining walls or
embankments without first consulting a professional engineer
to ensure the ground is capable of supporting the weight of
the full tank.
- Ensure the surface of the site is free
from sharp objects or stones and is compacted.
- Spread a thin layer (approx. 20-40mm)
of 3mm metal/crusher dust – bedding sand can be used
but is prone to erosion – evenly over the level ground,
at least 500mm more than the diameter of the tank. Once it
is compacted and level you may then place the tank directly
on top of this material. To assist with reducing soil erosion,
back fill to first rib.
- Specifications for slab for 10,300 gal and 8,000 gal tanks:
• Slab must be at least 150mm bigger then the base diameter of the tank
• Slab must be at least 150mm thick with 2 layers of F82 mesh 75mm apart and a
thickening of 200mm wide and 200mm deep with Y16 reo bar at the bottom of
the thickening around the edge of the slab
• Slab must be 32 mpa concrete mix
• Ensure all plumbing from the outlets is well supported and cannot be knocked.
- Ensure the metal/crusher dust is contained
under the tank at all times and cannot be washed away. This
can be achieved by diverting all run-off water away from the
site and retaining the metal/crusher dust with some form of
retaining structure e.g. cement strip, rocks or sleepers.
- A flexible coupling must be fitted to each outlet to validate the guarantee.
- For stand applications, ensure the stand
is designed to carry the weight of a full tank. Support slats
on the stand should be no further than 20mm apart.
- For concrete slab applications, the
slab must be at least 15cm wider than the base diameter of
the tank and at least 15cm thick with 2 layers of F82 mesh
75mm apart and a thickness of 20cm wide and 20cm deep, with
Y16 reo bar at the bottom of the thickening around the edge
of the slab and a 32 mpa concrete mix. If in doubt of soil
stability, you must consult a civil engineer and they will
design the slab accordingly.
- Ensure all plumbing from the outlet
is well supported and cannot be knocked (A flexible coupling
ensures no strain is applied to the outlet).
- Ensure all overflows are plumbed away
from the tank site to reduce the possibility of erosion.
Your Clark Polyethylene Tank requires very little maintenance,
simply check the site for any erosion and remove leaves and
other debris from the roof, inlet and overflow at regular
intervals.
TOP
|